Visayas power grid remains vulnerable despite return of 338-MW Cebu plant capacity

By PR | 03:16 PM November 24, 2026 

Many power line towers against a hazy sky. Photo: Winston Chen

The return of major power-generating units has improved electricity supply in the Visayas, but recurring grid alerts have highlighted the region’s limited reserves and continued dependence on imported power, particularly as demand in Cebu continues to rise.

The return to service of both 169-megawatt (MW) units of Therma Visayas Inc. (TVI) in Toledo City restored a combined 338 MW to the Visayas grid. However, the improvement has not been enough to ensure a wider supply margin against unexpected outages and constraints in power imports.

After several days of normal operations, the Visayas grid was placed under yellow alert on Oct. 17 and 18, followed by red and yellow alerts on Oct. 20. Available capacity dropped to 2,468 MW against a peak demand of 2,545 MW. Another yellow alert was issued on Nov. 4.

At a Sept. 21 joint briefing of the House committees on Energy, Visayas Development and Legislative Franchises, National Grid Corp. of the Philippines (NGCP) Visayas System Operations head Neil Martin Modina reported improving grid conditions following the return of TVI’s first 169-MW unit. The second unit returned shortly afterward.

But Energy Secretary Sharon Garin warned lawmakers during an Oct. 3 congressional hearing in Bacolod City that the Visayas had gone too long without sufficient new baseload power plants.

“Even with the absence of just a single power plant, we will go on alert and that is not good for business,” Garin said.

Cebu’s supply gap

The vulnerability is particularly evident in Cebu, where electricity demand is approaching 1,300 MW, compared with about 900 MW of generating capacity within the island, according to figures presented by Modina.

The shortfall makes Cebu dependent on electricity transfers from other parts of the Visayas and, when available, from Luzon and Mindanao.

Modina said the Luzon-Visayas interconnection, which has a nominal transfer capacity of about 440 MW, was at times carrying only around 250 MW as NGCP maintained contingency requirements and voltage stability.

The planned Cebu-Leyte Interconnection Lines 3 and 4, designed to add 1,200 MW of transfer capability, are expected to provide more options for moving electricity across the grid. However, additional transmission capacity will also require sufficient power generation to fully utilize the network.

Storage, new power plants eyed

With new dependable generation expected to take several years to come online, the Department of Energy (DOE) is looking at battery energy storage systems and demand-side measures to help stabilize supply.

Garin said renewable energy already accounts for about 45 percent of the Visayas generation mix. However, solar and wind output varies depending on weather and time of day, while electricity demand often peaks in the evening.

Battery storage systems can help address this mismatch by storing excess electricity and releasing it when demand increases.

The Energy Regulatory Commission (ERC) recently granted provisional authority for East Asia Utilities Corp.’s 44.72-MW battery energy storage system in Mactan to provide up to 13 MW each of firm regulating and contingency reserves to the Visayas grid. Other storage projects are also being developed in Toledo and Naga.

Energy conservation, distributed solar installations and other demand-management measures are also being considered to ease pressure during peak consumption periods.

For the longer term, Garin identified two proposed coal-fired power projects in Cebu with a combined capacity of 257 MW during the Oct. 12 Cebu Energy Summit.

These include the 150-MW expansion of TVI’s existing Toledo facility, targeted to begin commercial operations in 2028, and the 107-MW project of Cebu Energy Development Corp., targeted for 2029.

Garin said exemptions to the government’s moratorium on new coal-fired power plants could be considered under existing policies, particularly for projects that meet requirements related to energy security.

The DOE has maintained the coal moratorium but allows qualifying projects that have secured non-coverage or meet the requirements for committed expansion projects to proceed under the existing policy framework.

The two projects form part of the longer-term supply development plan for Cebu, alongside proposed gas-fired and renewable energy facilities.

Demand continues to rise

The need for additional power capacity is becoming more urgent as Cebu’s economy and electricity consumption expand.

During the Cebu Energy Summit, Garin said Cebu’s electricity demand was growing by about 14 percent annually, more than twice the roughly 6-percent growth recorded elsewhere in the country. Cebu accounts for about 42 percent of electricity demand in the Visayas.

“Cebu is the fastest growing. We don’t want Cebu’s economy to slow down because of electricity challenges,” Garin said.

ERC Executive Director Nancy Aurora Fajardo has also described the Visayas and Mindanao as emerging centers for manufacturing and technology, with expanding factories, data centers, logistics hubs and other energy-intensive developments.

Fajardo said the challenge facing the power sector was no longer simply ensuring adequate electricity supply but also improving the system’s flexibility.

“Today’s challenge is no longer simply supply adequacy, but system flexibility,” she said.

The return of TVI’s 338 MW has demonstrated the importance of dependable generation to the Visayas grid. However, the subsequent yellow and red alerts showed that the region remains exposed to supply disruptions.

With demand continuing to grow and major new generating facilities not expected until 2028 onward, the challenge for the Visayas is to build sufficient generation, expand transmission capacity and improve energy storage to ensure that electricity supply can keep pace with the region’s economic growth.